Facts & Figures


A few facts and figures about America's most ambitious public works project:

Cut away view of underground construction.Traffic 
Dirt
Concrete and steel 
First, most, biggest
Parks and open space
Underground Utility Relocation 
Odds and ends
 


Traffic

The elevated Central Artery had just six lanes. The new underground expressway has eight to ten lanes.

Altogether, the CA/T project built 161 lanes miles of highway in a 7.5 mile corridor, about half in tunnels, including four major highway interchanges.

The old road had 27 on- and off-ramps; the new one has just 14. With an improved surface street system, local traffic exits the main highway and distributes itself on surface roads while through traffic moves more easily under the city.

The elevated highway carried about 75,000 vehicles a day comfortably when it opened in 1959. By 2000, it carried more than 190,000, quite uncomfortably. Traffic jams lasted eight to ten hours a day, with an accident rate four times the national average for urban interstates. If nothing were done, traffic would have jammed in stop-and-go misery for 15 to 16 hours a day -- every waking hour -- by 2010.

The underground Central Artery will carry about 245,000 vehicles a day by 2010, with the Ted Williams Tunnel carrying about 98,000 vehicles a day. There will be normal urban rush hours of a couple of hours in the morning and evening on the underground expressway, with traffic moving at about 30 mph.

Back to the Top


Dirt

The project is excavating a total of 16 million cubic yards of dirt, enough to fill Foxboro Stadium (where the New England Patriots football team and Revolution soccer team play) to the rim 15 times.

About two-thirds of the dirt was trucked to landfills and other sites. Moving all that dirt took more than 541,000 truckloads. If all those trucks were lined up end to end, they'd back up 4,612 miles. That's all the way to Brasilia, capital of Brazil, as the crow flies, or to the Panama Canal strictly over land.

The rest of the dirt, more than 4,400 bargeloads of it, went  to Spectacle Island in Boston Harbor, where an old dump was capped to make way for a new park.

Nearly 3 million cubic yards of clay was made available to cities and towns to cap landfills that had reached capacity.

For more about what was dug, see "What are we Digging."

Back to the Top


Concrete and steel

The project placed 3.8 million cubic yards of concrete, enough to build a sidewalk three feet wide and four inches thick from Boston to San Francisco and back three times.

The project installed more than 26,000 linear feet of steel-reinforced concrete slurry walls, which formed the walls of the underground highway as well as the supports for the elevated highway during construction. That's five miles of slurry walls, the largest application of this construction technique in North America, all resting on bedrock up to 120 feet below the streets of the city.

Reinforcing steel used in the project would make a one-inch steel bar long enough to wrap around the earth at the equator.

Elevated Central Artery demolition will remove enough structural steel to make five Tobin Bridges.

Back to the Top


First, most, biggest

The South Boston connection (or interface) between the underwater section of the Ted Williams Tunnel and the land-based approach was built in the widest and deepest circular cofferdam in North America. A ventilation building was built inside the cofferdam, a  watertight structure from which water was pumped so that construction could take place inside.

The Ted Williams Tunnel interface in East Boston between the land-based approach and the underwater portion is 90 feet below the surface of Boston Harbor, the deepest such connection in North America.

The project's seven-building ventilation system is one of the largest highway tunnel ventilation systems in the world.

Traffic using the Metropolitan Highway System (including the underground Central Artery, the Ted Williams Tunnel, and the Mass Turnpike out to Route 128) 8is  monitored by the most advanced traffic management and incident response system in the world. Radio and cellular phone signals are re-broadcast into the tunnels.

The Leonard P. Zakim Bunker Hill Bridge is the widest cable-stayed bridge in the world and the first hybrid and asymmetrical design in the United States, using both steel (in the main span) and concrete (in the back spans).

The project required the largest use of segmental bridge construction and the largest application of steel box girders in the United States.

Crossing the Fort Point Channel included the most extensive use of concrete immersed tube tunnels in the United States, the first installation of jacked vehicle tunnels in North America (and one of the largest in the world), and the second use of soil mix construction on the East Coast (the first use came in East Boston on the Ted Williams Tunnel).

The project included the largest geotechnical investigation, testing and monitoring program in North America. The purpose was to identify conditions in the path of tunneling work, and help prevent buildings from settling during the digging.

Back to the Top


Parks and open space

The project will create more than 300 acres of new parks and open space, including 27 acres where the existing elevated highway stood, 105 acres at Spectacle Island, 40 acres along the Charles River, and 7 acres as part of an expanded Memorial Stadium Park in East Boston.

Three quarters of the 27 downtown acres will remain open. The rest will be set aside for modest development, including retail, commercial, and housing uses in low-rise buildings.

More than 2,400 trees and 26,000 shrubs were planted at Spectacle Island. Another 2,400 trees and more than 7,000 shrubs will be planted downtown.

Back to the Top


Underground Utility Relocation

The project's underground utility relocation program moved 29 miles of gas, electric, telephone, sewer, water, and other utility lines maintained by 31 separate companies. All told, about 5,000 miles of fiber optic cable and 200,000 miles of copper telephone cable was installed.

The Central Artery/Tunnel Project used the latest applications for preventing damage to Boston's vital subsurface infrastructure. Damage prevention efforts were continually being updated.

dense utility location
This is one of the most densely populated utility locations in the city at the intersection of Congress Street and Atlantic Avenue. Shot in 1998, this shot shows nine live utilities and one abandoned utility in one typical trench excavation.


These renderings below show the jumbled mix of utilities before construction, and the lines now set in modern utility corridors.

Utilities Utilities

Click either of these two image for larger versions.

Also, see a photo and details about a special compressed-air excavator (in our equipment section) aimed to cut utility damage.

Related link: Underground Focus Magazine.

Back to the Top


Odds and ends

Because of the new highway system, Boston's carbon monoxide levels will drop 12 percent citywide. How can a road carrying more cars reduce pollution? Because it will keep traffic moving, so that emissions will be reduced significantly.

The cable-stayed bridge across the Charles River used 1,820 miles of steel wire to form the seven-wire strands that are in turn bound together to form the support cables, the largest a foot in diameter.

About 150 cranes were in use project-wide.

The first 25 percent of construction took five years to complete, the second 25 percent took about two years to complete (the half-way point was reached in the spring of 1999). By the summer of 2004, construction was 94 percent complete.

During the peak of construction (1999 through 2002), about $3 million of work was completed each day.

At the peak of construction activity about 5,000 construction workers were on the job.

The deepest point of the underground highway is 120 feet down, beneath the Red Line subway tunnel at Dewey Square (Atlantic Avenue and Summer Street). The highest point is at State Street, where the highway passes over the Blue Line subway tunnel and the roof of the highway is the street above.

The project included 118 separate construction contracts, with 26 geotechnical drilling contracts.

Back to the Top