June 2005 - A brief history and review of pending issues
The Central Artery/Tunnel Project was conceived in the early 1980s. After being
approved on a state and federal level, construction began in 1991. Over the years,
both the scope of the project and its cost have grown, but the price has remained
steady at $14.625 billion since Matthew Amorello took over as Chairman of the
Massachusetts Turnpike Authority in 2002. Despite the many improvements the "Big
Dig" has already delivered to the motoring public, it's important to keep in mind
that THE PROJECT IS STILL UNDER CONSTRUCTION.
Accountability
In addition to taking steps to successfully contain the cost of the project and
keep it on schedule, Chairman Amorello has required that designers and contractors
that are responsible for any errors be held accountable for their work, insisting
that they deliver what they are being paid to deliver and live up to all their
contractual obligations.
In addition to overseeing and completing the CA/T Project, Chairman Amorello
has also worked to restore credibility to the Project following the well-publicized
non disclosure of increases to the Project cost in the late 1990s. As part of
that effort, the Turnpike Authority has tried to be as transparent as possible
in its oversight of the "Big Dig" taking such action as posting the Project Management
Monthly (PMM) Reports on our website; and following the breach in the I-93 North
Tunnel last fall, the Chairman committed to weekly press briefings/updates to
keep the public informed of the progress with ongoing inspections of all the slurry
wall panels.
The initial panel inspections are now complete, though some follow-up inspections
continue. In a continuing effort to keep the public informed, however, the Chairman
has directed the Project to offer updates on water infiltration - which is a separate
and distinct issue from defective slurry wall panels - and to offer insight into
other issues that need to be resolved on the Project before the MTA accepts the
final work from the contractors. These updates will include water management indicator
reports, which are sent regularly to the Federal Highway Administration and the
U.S. Department of Transportation's Inspector General so they can monitor the
Project's progress with water management, and other reports that help explain
remaining challenges and progress as we work toward completion. There are currently
more than 1,000 punch list items to either complete or correct before the MTA
accepts the final work from the contractor.
How issues are addressed
*When an area of concern is identified by Project personnel to be an issue tied
to construction, the first course of action is getting the responsible contractor
to take care of the issue and complete necessary work that will provide a lasting
product that is in full compliance with their contract. We direct the contractor
to do the necessary work, if they refuse, we bring in other contractors to do
the work and backcharge the original contractors for the cost. In instances where
the area of concern is the result of errors or omissions during the design phase,
and the designer will not agree to cooperatively devise corrective action and
absorb any extra costs the Project has incurred, the issue will be referred for
potential cost recovery.
Over the course of the last eight months, the issue of water infiltration in
the Central Artery tunnels has been a matter of great interest and scrutiny. Water
infiltration occurs in various locations within the tunnels and is attributable
to a variety of issues - many of them expected as part of ongoing construction. In
fact, a significant amount of the water being removed from the tunnels via our
pump stations is the result of either active construction work or regularly-scheduled
tunnel washing activity.
Remember, this IS STILL A WORK IN PROGRESS, and there are areas of active construction
where the tunnel roof is not finished, allowing water to get inside.
These include:
-The future on-ramp from Essex Street to I-93 North.
-The future South Station exit from I-93 South.
In addition, there are various areas along the downtown corridor where waterproofing
remains to be done. There are also conduit lines and manhole covers that haven't
yet been sealed, which also generate a significant amount of the water infiltration
which we continue to deal with as we work to complete the Project. Again, those
avenues for water infiltration will no longer exist after the Project is completed.
Background on water management indicators
It is important to keep in mind that there are two different issues which are
talked about in our Water Management Indicator Reports. One is water infiltration,
which will be resolved as a final phase of construction. The other issue is defective
slurry wall panels, an unacceptable construction element; neither of these impacts
the structural integrity of the tunnels.
Slurry wall defects
First we look at the issue of defective slurry wall panels which we became acutely
aware of after the breach of September 15
th 2004. This event provided the footage of water pouring out of a tunnel wall,
which has been a fixture on television newscasts for months. This was one of two
breached panels in the 2,000 slurry wall panels in the I-93 tunnels, and by far
the most significant. To put this into perspective, the September 2004 incident
produced about 250 gallons of water per minute, while the other breach had a flow
of about 5 gallons per minute [it is important to note: we have 11 pump stations
in the CA/Tunnel network and each station can handle an average of approximately
1,000 gallons per minute, so there was no concern of flooding from these incidents].
Chairman Amorello was outraged after the September breach and ordered a full inspection
of all 2,000 panels to determine if there were additional issues. During those
inspections 167 other panels were found to have less serious defects, and ALL
are being repaired. [The second panel deemed to be a breach occurred in January
of 2004 when water on the roadway caused icing. This event was not classified
as "a breach" until the internal Project investigation that followed the September
event found similarities between the two events.]
The inspections of the slurry walls have been done by Bechtel/Parsons Brinckerhoff,
the Project's Management Consultant at their time and their expense, and the panel
repairs are being performed at the expense of the responsible contractor.
Water Management/Injection Grouting
The water management program deals with water infiltration which currently can
be characterized as trickling and dripping. This is what has been alluded to in
media reports saying the Project has "hundreds of leaks." These areas are nothing
of the caliber of the breached or defective panels talked about above, and grouting
them is a normal part of construction.
This year, as in past years, we have been conducting an inspection of the I-93
tunnels to monitor the progress of the Project's water management program. More
than 9,000 of the 9,500 [94%] roof girder bay ends [where tunnel walls meet the
roof] have been inspected and 820 have been found to have wet [trickling or dripping]
areas. Since March 30
th the Project has been using the 820 figure as the baseline to measure the progress
of the water management/grouting program and we will continue to do so during
2005. As of the end of May that count has been reduced to 550 and while this
is a good indicator of how the contractor's production/effectiveness is monitored,
another yardstick is the volume of water entering the tunnels at these locations;
the volume appears to be lessening as well with continued injection grouting and
as additional sources of water related to construction such as open roof sections
and conduit bays are sealed. In addition to the wet areas there are more than
1,600 other roof girder bay ends where the 2005 inspection has shown what we refer
to as "seeps" in our reporting and this means there is dampness [the Project criteria
for classifying a roof girder bay end as seeping is: "Sheen is visible having
a shining appearance, when wiped away, the sheen reappears, but no water is running
or dripping"]. As grouting continues those damp areas that are near or against
steel take priority over those that are not. While "substantial completion" of
road construction is slated for the fall of this year, the remainder of the work,
which will include the injection grouting of some of these areas, will continue
through the following months as has been planned. This water management program
is used to monitor the contractor's progress in meeting their contractual obligation
in completing the grouting work. *As noted in the section above: We direct the
contractor to do the necessary work, if they refuse, we bring in other contractors
to do the work and backcharge the original contractors for the cost.
It is important to note that there will always be/and was always expected to
be a water management element to the maintenance plan for the CA/T system, as
there would be with any tunnel system, particularly those of slurry wall construction.
I-90 Tunnels
With regards to the I-90 portion of the Project, we are monitoring and inspecting
areas in the Ted Williams and Fort Point Channel Tunnels as well. In particular
we have been monitoring an area near the Fort Point Channel since repair work
was done after the tunnel opened in 2003. Crack gauges were subsequently placed
on a flexible pavement joint in that area to monitor its movement. This past
winter the joint expanded more than in the past, and this spring more water flow
was found. It was determined the fix was not performing as anticipated. The joint
is too reactive to temperature changes, which have caused water infiltration and
stress cracks in tiles and in a concrete column. This is not a safety issue,
as this column continues to perform its designed role. In fact, this column could
be removed completely and it would not affect the structural integrity of the
tunnel.
Also on the I-90 portion of the Project we have experienced an inflow of approximately
4-8 gallons of water per minute at each of two immersed tube tunnel joints. While
this appears to be is less of an issue as the temperatures warm, a long-term solution
is being developed to allow these joints to perform in the way they were expected
to. This water is piped directly from the two locations to a pump station. The
water is not on the roadway and is a very manageable amount for the pump station
to handle. That being said, while neither of these issues is one of safety, they
are both UNACCEPTABLE and we will hold the responsible party or parties accountable
to the full extent of their contract to insure these issues are resolved.